AUMUND’s electrified Linear Calcination Conveyor (eLCC) technology has been chosen by the European Commission for funding. The first industrial scale plant shall be installed at a HOLCIM facility in Greece and will have an annual production capacity of 150,000 tons of calcined clay. It combines a high-temperature, electrified calcination process with AUMUND eLCC technology to produce low-carbon calcined clay. The process will be powered by a hybrid renewable energy system combining solar photovoltaic (PV) generation with a battery energy storage system (BESS). About 320 European net-zero technology projects have been supplied, only 77 will receive a funding, totaling €3.4bn. The project has now entered the grant preparation phase with the European Commission, with the grant agreement expected to be signed in March 2027.